CODE
Rev.No 00
HSE PROCEDURE
PAGE 1 of 2
TITLE: - Permit to Work Procedure
OBJECTIVE: - To Create a process to manage hazardous work safely.
To Create a process that integrates risk assessments, hazardous
energy isolations (lockout/tagout), and permit coordination.
To Ensure work is scoped and risk is analyzed.
To Gain real-time visibility to coordinate activity.
To Obtain data to optimize processes and conduct investigative work.
SCOPE Applicable to all critical activities associated with CGD Projects at IRM
Energy Private Limited, its contractor & sub-contractors.
PROCEDURE Permit to Work
RESPONSIBILITY ACTIVITY DESCRIPTION REF DOC./NOTES
Permit to Work
Requester/Concern For all the critical activities involved in city
Department gas distribution projects permit to work is Ref.- HSE/WP-01
/Contractor required.
Working Agency (Contractor) will fill the
work permit & inform the HSE department
for the permit verification.
Site HSE Engineer will physically verify the
place, where the work will be performed
and check all the control measures (Safety
measures) are in place before signing on
the work permit.
DATE OF ISSUE PREPARED BY / VERIFYIED BY APPROVED BY
HSE & Technical Department
CODE
Rev.No 00
HSE PROCEDURE
PAGE 2 of 2
After the verification is done by the officials
Project of the HSE department, the Project
Head/Manager/O&M Head/Manager/ O&M Department will
Department approve the work permit and sign on the
permit before starting of the work.
After the work is completed, the permit will
Requester/Working be closed by the permit requester i.e.
Agency/Contractor. working agency/contractor.
Mandatory Note –
1. Permit to work must be issued for all critical activities associated with CGD Projects
2. Permit to work will be valid for duration of single shift only.
3. The master copy (white copy) of the work permit must be documented and maintained by the
requester/concern dept. Second copy (Pink copy) must be submitted to the HSE department and
the third copy (Yellow copy) must be available at the site.
OUTPUT REFERENCE CODE/FORMAT: HSE/WP/01
Mention in REF DOC. /NOTES
RELATED DOCUMENTS
Work Permit
MONITORING CRITERIA
Site Inspection